Title:
|
ORD Approp $750,000 from the Drainage System Rehab – DSR General Capital Projects Proj to the Silver St Drainage Improvements Proj to Pay for Removal & Replacement of the Existing Storm Drainpipe & Inlet System on Silver St Beginning Near 7th St & Ending at the Outlet of Hogan’s Creek in Klutho Park; Amend the 2023-2027 5-Yr CIP Appvd by Ord 2022-505-E to Reflect This Approp of Funds from the Drainage System Rehab – DSR General Capital Projects Proj to the Silver St Drainage Improvements Proj (B.T. 23-020) (Staffopoulos) (Introduced by CP at Req of Mayor)
11/22/22 CO Introduced: F, TEU
12/6/22 F Read 2nd & Rerefer
12/6/22 TEU Read 2nd & Rerefer
12/13/22 CO PH Read 2nd & Rerefer
1/4/23 F Amend/Approve 7-0
1/4/23 TEU Amend/Approve 7-0
1/10/23 CO Amend/Approve 18-0
Public Hearing Pursuant to Ch 166, F.S. & C.R. 3.601 – 12/13/22
|